Planning and Construction Info & News Page




Latest News

Site prepared and foundations prepared - mid Oct
Tower crane erected - Sunday 18th October
Steel frame and ground floor structure - mid Oct to mid Nov

crane

crane

Who is involved

Contractor: CM Cadman Limited
Project Management: Barker Associates
Architect: SHMG Architects
Other consultants: eg Quantity Surveyors, Electrical & Mechanical Engineers, Tree specialists ... and Solicitors

The parishes of St. Joseph and St Michael are both represented by committees with parish volunteers in two key areas:

St. Joe's representatives are:

Planning & Design

Canon Eddie Matthews
Tony Barrance
Nando Braz
Bernard Judge
Tony Wood

New Centre Management

Canon Eddie Matthews
Nando Braz
Yvonne Fordyce
Tony Wood

The above are supported by Tim Gilbert, Diocese of Westminster Property Manager Manager


Why it has taken so much longer...

  • The project is unique with two churches under differing church legal systems
  • Complex access arrangements to the site for all materials and utilities
  • Land purchase and Rights of Way - like a patchwork quilt, owned by two legal entities
  • Local Authority and Highways consents (since Mar 2009)
  • Changes to Charities Act effected from Jan 2009 (imposed a change on C of E Parish councillors' status)
  • To minimise financial risk a convoluted event sequence had to be followed

Project Time Line 2009

24th August
Works
Commence

11th Sept
Site Prepared

16th Oct
Foundations
Prepared

18th Oct
Tower Crane
Erected

13th Nov
Steel Frame
& Ground Floor

11th Dec
First Floor
Steel Deck

Project Time Line 2010

26th Feb
Main Roof

5th March
First Fix

14th May
Second Fix

11th June
Decorations

15th June
Centre
completed