Site prepared and foundations prepared - mid Oct
Tower crane erected - Sunday 18th October
Steel frame and ground floor structure - mid Oct to mid Nov
Contractor: CM Cadman Limited
Project Management: Barker Associates
Architect: SHMG Architects
Other consultants: eg Quantity Surveyors, Electrical & Mechanical Engineers, Tree specialists ... and Solicitors
The parishes of St. Joseph and St Michael are both represented by committees with parish volunteers in two key areas:
St. Joe's representatives are:
Canon Eddie Matthews
Tony Barrance
Nando Braz
Bernard Judge
Tony Wood
Canon Eddie Matthews
Nando Braz
Yvonne Fordyce
Tony Wood
The above are supported by Tim Gilbert, Diocese of Westminster Property Manager Manager
Why it has taken so much longer...
|
Project Time Line 2009 | |||||
|
24th August |
11th Sept |
16th Oct |
18th Oct |
13th Nov
Steel Frame |
11th Dec |
|
Project Time Line 2010 | |||||
|
26th Feb |
5th March |
14th May |
11th June |
15th June
Centre |
  |